The 500 kV circuit 3 transmission line was inaugurated on August 29 |
The inauguration of the line with a total length of approximately 519km marks the 79th anniversary of the August Revolution and National Day (September 2).
The transmission line was put into operation on late August 27. Its construction began on January 18, 2024. The project traverses nine provinces and cost around VND22 trillion ($916 million).
The project will help reduce the load on existing 500kV transmission lines, especially when transmission capacity is high on the north-central interface (at times when Northern hydropower plants generate low output).
The transmission line will also help increase stability reserves on the north-central interface, in combination with the 500kV Quang Trach - Quynh Luu - Thanh Hoa - Nam Dinh I TPP - Pho Noi transmission lines. This will contribute to supplementing power from sources in the northern central region to the load centre in the northern region.
It also raises the transmission capacity from the current 2,200MW to approximately 5,000MW, equivalent to over 20 billion kWh of commercial electricity supplied to the north annually.
The project will contribute to ensuring electricity supply for the northern region this year and the following years.
The 500kV circuit 3 transmission line was inaugurated on August 29 |
Earlier, Prime Minister Pham Minh Chinh called for the completion of the line on schedule. Ministries, agencies, localities, and units redoubled their efforts, strengthened unity, and boosted their determination and effectiveness to complete the project with the highest sense of responsibility.
500kV transmission line project from Quang Trach to Pho Noi Investor: National Power Transmission Corporation (under EVN) Total investment: about VND22 trillion ($916.6 million) Scale: 2 circuits of 500kV transmission line, about 519km long. Starting point is 500kV Quang Trach switchyard (Quang Binh), ending point is 500kV Pho Noi substation (Hung Yen). Engineering consultant: Power Engineering Consulting JSC 1, 2, 4 and Institute of Energy Project Management Board for Northern Power Projects on behalf of EVNNPT manages two sections: Nam Dinh I Thermal Power Plant – Thanh Hoa and Nam Dinh I Thermal Power Plant - Pho Noi. Project Management Board for Central Power Projects on behalf of EVNNPT manages two sections: Quang Trach – Quynh Luu and Quynh Luu - Thanh Hoa |
500 kV transmission line Vung Ang-Quang Trach-Doc Soi-Pleiku 2 officially energises Energising the third circuit of the 500kV transmission line Vung Ang-Quang Trach-Doc Soi-Pleiku 2 will contribute to undertaking electricity supply and energy security for the South and releasing the power of renewable energy projects. |
PM mandates transmission line to be operational by September 2 Prime Minister Pham Minh Chinh has set a firm deadline to complete the 500 kV transmission line (Phase 3) by September 2, with an inauguration scheduled for National Day this year. |
What the stars mean:
★ Poor ★ ★ Promising ★★★ Good ★★★★ Very good ★★★★★ Exceptional