Deputy Prime Minister Tran Hong Ha approved the policy for the Nam Dinh I-Thanh Hoa thermal power plant's 500kV line on October 23, with the National Power Transmission Corporation (EVNNPT) assigned as the investor.
This project is one of four components for the 500kV Circuit 3 line, which combines Quang Trach-Quynh Luu, Quynh Luu-Thanh Hoa, Nam Dinh 1-Thanh Hoa, and Nam Dinh 1-Pho Noi.
According to Vu Tran Nguyen, deputy general director of EVNNPT, the 500kV line for Circuit 3 plays a vital role, so it needs to be implemented promptly and put into operation as soon as possible to contribute to ensuring power supply for the North.
“The approval is an important legal procedure, which now forms the basis for EVNNPT to implement the next steps. This positive result comes thanks to Prime Minister Pham Minh Chinh, the Ministry of Planning and Investment, the Ministry of Industry and Trade, the Committee for the Management of State Capital at Enterprises, and the localities accelerating the procedures for the project,” Nguyen said.
Currently, the locations where the Circuit 3 500kV line passes through are closely coordinating with ministries and central agencies to complete additional procedures and clarify dossiers on policies to change land use rights for forest areas, ensuring the compatibility of projects with local planning.
Along with that, EVNNPT is completing documents to ensure the approval of the Environmental Impact Assessment Report (EIA) as soon as the Prime Minister green-lights the investment policy. Feasibility study reports will be completed and submitted to the authorities for appraisal immediately after the investment policy and EIA are approved.
"After the prime minister approves the investment planning for the 500kV line project for the Nam Dinh I-Pho Noi thermal power plant, EVNNPT will immediately implement the project to ensure its goals are met. In addition, we will continue to coordinate with ministries and branches to complete legal procedures to implement the remaining three projects according to the prime minister's directions," Nguyen said.
EVNNPT has arranged the simultaneous implementation of the project’s work and allocated adequate capital. It has coordinated closely with localities on site clearance work, and is gathering human resources, machinery, and materials to start construction immediately, contributing to ensuring the electricity supply for the North into the future.
Samsung meets with EVNNPT to ensure stable power supply Choi Joo Ho, general director of Samsung Display Vietnam, and the representatives of some of its vendors are working with National Power Transmission Company (EVNNPT) to discuss the power supply situation coming up to their peak production season. |
EVNNPT in solid position after 15 years National Power Transmission Company (EVNNPT) has made significant achievements and contributed greatly to ensuring national energy security in the 15 years since its establishment. |
EVNNPT accelerates construction of Nho Quan-Phu Ly-Thuong Tin transmission line National Power Transmission Corporation (EVNNPT) is expediting the construction of the 500/220kV Nho Quan-Phu Ly-Thuong Tin transmission line. |
EVNNPT to loan $675 million for Quang Trach-Pho Noi 500kV line National Power Transmission Corporation will mobilise loans worth $675 million for part of the construction of the Quang Trach-Pho Noi 500kV transmission line project. |
EVN and EVNNPT to upgrade power transmission lines in Thai Binh Vietnam Electricity (EVN) will co-operate with National Power Transmission Corporation (EVNNPT) and Thai Binh People’s Committee to resolve the issues relating to the power transmission lines in the northern province. |