Quynh Luu-Thanh Hoa 500kV Circuit-3 transmission line operational

August 19, 2024 | 16:49
(0) user say
The National Power Transmission Corporation (EVNNPT) and the Central Vietnam Power Project Management Board (CPMB) in collaboration with relevant units sent electricity to the Quynh Luu - Thanh Hoa 500kV Circuit-3 transmission line on August 19 morning.
Quynh Luu - Thanh Hoa 500kV Circuit-3 transmission line operational
Representatives of EVNNPT and related units at the ceremony to send electricity to the Quynh Luu - Thanh Hoa 500kV Circuit-3 transmission line. (Photo: VGP)

As part of the 500kV Circuit-3 power transmission line project, which runs from Quang Trach in the central province of Quang Binh to Pho Noi in the northern province of Hung Yen, the line is invested by the EVNNPT, managed by the CPMB, and operated by Power Transmission Company 1 (PTC1).

The 92-km line passes through the central provinces of Nghe An and Thanh Hoa. Its construction began on January 18.

It is expected to reduce the load and avoid overloading of existing 500kV lines and help improve transmission capacity, thus contributing to strengthening capacity from power sources in the north-central region to the load centre in the northern region.

The completion and commissioning of the project meets the Prime Minister's directives, serving as a significant motivation for completing the entire 500kV Circuit-3 power transmission line project in the coming days.

Feasibility is a must for successful DPPA mechanism Feasibility is a must for successful DPPA mechanism

A July government decree permits many kind of renewable energy projects to engage in direct power purchase agreements without using Vietnam Electricity transmission line. Tran Dang Khoi, general director of Hero Future Energies Vietnam LLC under Hero Group, told VIR’s Oanh Nguyen about the impact of the policy on renewable energy firms and offered some proposals.

Ministry investigates wrongdoings at 32 solar and wind farms Ministry investigates wrongdoings at 32 solar and wind farms

The Ministry of Public Security has instructed Vietnam Electricity (EVN) to hand over documents related to 24 wind farms and eight solar power projects as part of an investigation into abuse of power among public officials.

PM mandates transmission line to be operational by September 2 PM mandates transmission line to be operational by September 2

Prime Minister Pham Minh Chinh has set a firm deadline to complete the 500 kV transmission line (Phase 3) by September 2, with an inauguration scheduled for National Day this year.

By VNA

What the stars mean:

★ Poor ★ ★ Promising ★★★ Good ★★★★ Very good ★★★★★ Exceptional