Construction of Nhon Trach 3 and 4 thermal power plants behind schedule

February 28, 2023 | 16:04
(0) user say
The construction of the Nhon Trach 3 and 4 thermal power plants is behind the initial schedule because of barriers to land clearance and capital mobilisation.
Construction of Nhon Trach 3 and 4 thermal power plants behind schedule
The construction site. Photo: dongnai.gov.vn

According to Thai Thanh Phong, deputy director of Dong Nai Department of Industry and Trade, the Ministry of Industry and Trade has yet to issue the power price framework that will be applied to the liquefied natural gas projects.

“The capital mobilisation also faces barriers because these projects are not guaranteed by the government for loans and the long-term contracts have yet to be committed into the power purchase contract,” Phong said.

“At Nhon Trach 3 thermal power plant, the initial electrical connection plan has to be adjusted due to obstacles in land clearance. The adjusted plan has to wait for approval to be added into the national power master plan,” he said.

The Nhon Trach 3 and 4 power plants are set to be built in Ong Keo Industrial Park in the southern province of Dong Nai. With its favourable location and the solid infrastructure of the Southern Key Economic Zone, Dong Nai has become the focus of attention for property developers in recent years.

The projects have a total investment capital of $1.4 billion. The investor, PetroVietnam Power Corporation, was committed to ensuring sufficient capital for the projects, including 25 per cent from equity and 75 per cent from loans from export credit. $300 million will come from foreign commercial sources and around $170 million from domestic banks.

Previously, the investors targeted starting the construction of these two thermal power plants in April 2022. They expected that the first turbine would come into operation in October 2024, with the second running in April 2025. The plan was for the boiler system to be established in late 2023.

PetroVietnam seeks new EPC contractor for 1,200MW Long Phu 1 thermal power plant PetroVietnam seeks new EPC contractor for 1,200MW Long Phu 1 thermal power plant

State-run oil and gas group PetroVietnam is looking for a new EPC contractor for the 1,200MW Long Phu 1 thermal power plant, which is located in the Mekong Delta province of Soc Trang.

HDF Energy inks MoU with PTSC to build hydrogen power plants HDF Energy inks MoU with PTSC to build hydrogen power plants

Hydrogène de France SA (HDF Energy) has signed an MoU with PetroVietnam Technical Services Corporation (PTSC) to jointly develop, finance, and build HDF's hydrogen power plants in Vietnam.

$1.8 billion Quang Trach power plant faces land clearance issues $1.8 billion Quang Trach power plant faces land clearance issues

Quang Trach 1 thermal power plant, which is invested by EVN, is facing difficulties in land clearance.

Thermal power plants face risk of coal shortage Thermal power plants face risk of coal shortage

Many thermal power plants are facing the risk of coal shortages because supply has been interrupted.

By Ha Vy

What the stars mean:

★ Poor ★ ★ Promising ★★★ Good ★★★★ Very good ★★★★★ Exceptional