Feedback sought on Long Thành Airport design

January 16, 2017 | 11:20
(0) user say
HCM City - The Aviation Airport Corporation of Việt Nam (ACV) has started collecting feedback from the local community in HCM City regarding the architectural plan of  Long Thành International Airport’s passenger terminal from January 12 to 23, 2017.
The Aviation Airport Corporation of Việt Nam (ACV) has started collecting feedback from the local community in HCM City regarding the architectural plan of Long Thành International Airport’s passenger terminal from January 12 to 23, 2017.-VNS Photo

“The Government had appointed the ACV to be the investor for the passenger terminal. We are establishing the feasibility research for the first phase of the Long Thành International Airport’s passenger terminal,” Đào Việt Dũng, deputy general director of the ACV was quoted as saying on the government website.

The ACV had already organised a contest for the architectural plan of the Long Thành International Airport’s passenger terminal. There were 16 international and domestic companies taking part in the contest with nine plans.

The contest aimed to choose the most beautiful and feasible design that meets all required functions, as well as representing the special characteristics of the construction.

The most impressive plans included images of palm branches and water coconut – familiar images of the South’s culture - along with a bamboo roof – a Vietnamese symbol - for the public spaces of the Long Thành International Airport’s passenger terminal.

The collection of suggestions from the local community about architectural plan of the Long Thành International Airport’s passenger terminal was held in Hà Nội from November 28 to December 12, 2016, in the central city of Đà Nẵng from December 16 – 25 and in the southern province of Đồng Nai from December 28, 2016 to January 11, 2017.

The Long Thành International Airport project was divided into three stages. At the first stage, a runway and one passenger terminal along other supported works will be built to serve 25 million passengers and 1.2 million tonnes of cargo each year. The first phase will be finished by 2025.

At the second stage, one more runway and another passenger terminal will be constructed to serve 50 million passengers and 1.5 million tonnes of cargo a year. After the third phase, the airport will serve 100 million passengers and 5 million tonnes of cargo each year.

VNS

What the stars mean:

★ Poor ★ ★ Promising ★★★ Good ★★★★ Very good ★★★★★ Exceptional