![]() |
| Leaders of An Giang People's Committee held a field survey at Phu Quoc Special Economic Zone on March 31 |
The committee stated that the province has just submitted a report on the implementation of several power grid projects in Phu Quoc Special Economic Zone.
As of March 30, the 110kV Phu Quoc - South Phu Quoc power line project has a total length of over 19km (79 tower locations), and the land area to be acquired for this initiative is over 37,700 square metres. The locality handed over the land for 70 out of 79 towers.
The Phu Quoc - North Phu Quoc 110kV power line project has a length of nearly 20km (75 tower locations), with a land area of over 13,000 sq.m. To date, only 19 out of 75 towers have been handed over.
The Phu Quoc 220kV substation undertaking has a land area of over 49,500 sq.m. The local authorities completed the handover of 4.6ha of forest land and finalised the land compensation plan for 12 affected households.
Along with the achievements, the above projects still face some difficulties, such as the long power line route, which significantly affects organisations and households; the extensive field surveying and mapping work, while the land clearance workforce is limited.
Some households have not yet agreed to hand over their land. At the same time, the local authorities have not been able to review, adjust, and update land use changes on time, leading to many complications.
The An Giang provincial leadership has requested the government consider applying a special mechanism for implementing certain measures to expedite the project serving APEC 2027.
The province has committed to ensure the progress of land clearance by the deadline and to resolve any obstacles. The locality will coordinate with the electricity sector and relevant units to complete the projects on schedule to provide electricity to the island and welcome APEC 2027.
| Long Thanh Airport at risk of delays due to slow land clearance Long Thanh International Airport is facing a very real risk of falling behind its construction schedule as land clearance and relocation is only half completed against the deadline at the end of June. |
| Dak Nong to accelerate land clearance for wind power projects Dak Nong People’s Committee has promised to thoroughly deal with bottlenecks in land clearance to unlock wind power project development. |
| $1.8 billion Quang Trach power plant faces land clearance issues Quang Trach 1 thermal power plant, which is invested by EVN, is facing difficulties in land clearance. |
| Dong Nai hands over ground-phase 1 to develop Long Thanh International Airport On August 25, Long Thanh People’s Committee organised a ceremony to hand over ground-phase 1 for the construction of Long Thanh International Airport and the two road routes connecting the T1 and T2 terminals, to investors. |
| Land clearance for $2 billion Thai Binh LNG power plant set for completion in January 2025 Thai Binh authorities are working with the investor to complete site clearance for a $2 billion LNG power plant in the northern province by January 2025. |
What the stars mean:
★ Poor ★ ★ Promising ★★★ Good ★★★★ Very good ★★★★★ Exceptional