No more delays in construction schedule of Eastern Cluster of North-South Expressway

September 16, 2021 | 18:09
(0) user say
Vietnamese Deputy Prime Minister Le Van Thanh has ordered relevant ministries, agencies, and local authorities to ensure the construction schedule of the Eastern Cluster of North-South Expressway without a delay.
No more delays in construction schedule of Eastern Cluster of North-South Expressway
Deputy Prime Minister Le Van Thanh ordered no more delays in the construction of the Eastern Cluster of the North-South Expressway

The Deputy PM made the order at an online meeting on September 14 on the development of the Eastern Cluster of North-South Expressway with contractors, relevant ministries, the State Bank of Vietnam, as well as the 13 cities and provinces the project goes through.

He noted that more delays in the project construction would be acceptable. He asked local authorities to complete the site clearance in October 2021. Contractors will have to address sluggish construction while abiding by the rules on COVID-19 prevention and fight.

Cities and provinces, and relevant ministries are asked to create more favourable conditions for mining licensing procedures to ensure enough building materials for the project.

No more delays in construction schedule of Eastern Cluster of North-South Expressway
The meeting focused on solving the problems related to site clearance and lack of building materials facing the project

The Eastern Cluster of North-South Expressway comprises of 11 component projects, including eight funded by the state, and three public-private-partnership ones. Despite efforts, the project is facing some problems, with the two mainly being a lack of construction materials and site clearance.

According to the Deputy Minister of Transport, site clearance now meets 98.4 per cent of the total area. Thus far, 10 component projects have been kicked off. The remaining Cam Lam-Vinh Hao route is planned to start construction in October.

Currently, the barriers related to the licensing procedures for the mining of common building materials are yet to be solved. The project still lacks about 23 million cubic metres of land.

Duong Van Mau, deputy general director of Vinaconex, a contractor of the project, said that the company mobilised hundreds of equipment, technical staffs, and engineers to serve construction. However, due to a shortfall of building materials, it has to wait, causing losses and delaying the project. The contractor proposed local authorities to shorten mining licensing procedures to ensure enough building materials.

At the meeting, cities and provinces pledged to complete site clearance, and solve the barriers related to building materials, while working with relevant agencies on dealing with other problems.

State Appraisal Council for North-South Expressway to be establish State Appraisal Council for North-South Expressway to be establish
Vietnam signs contract of third PPP section of North-South Expressway Vietnam signs contract of third PPP section of North-South Expressway
Nghi Son-Dien Chau section of North-South Expressway to be kicked off this month Nghi Son-Dien Chau section of North-South Expressway to be kicked off this month
Government asks provinces to ensure sufficient materials for North-South Expressway Government asks provinces to ensure sufficient materials for North-South Expressway

By Bich Thuy

What the stars mean:

★ Poor ★ ★ Promising ★★★ Good ★★★★ Very good ★★★★★ Exceptional