EVNNPT accelerates 500kV transmission line from Quang Trach to Pho Noi

May 27, 2024 | 17:21
(0) user say
EVNNPT has mobilised more than 800 engineers and skilled workers to participate in erecting poles and pulling wires for the 500kV transmission line circuit 3 from Quang Trach to Pho Noi project to ensure the key national project is on time.
EVNNPT accelerates 500kV transmission line from Quang Trach to Pho Noi
EVNNPT mobilise 800 people to accelerate the 500kV transmission line circuit 3 from Quang Trach to Pho Noi

According to Vietnam Electricity (EVN), the weather is currently changing, so erratic rain, sunshine, and thunderstorms are causing difficulties for the construction of the 500kV circuit 3 line Quang Trach - Pho Noi project.

However, ministries, localities, EVN, and National Power Transmission Corporation (EVNNPT) are working together with contractors to try to overcome the problems and are determined to complete projects according to schedule.

To date, all column foundation positions and most anchorages have been handed over.

The investor urged contractors to import enough input materials, install more and optimise production lines, and increase human resources to work all days and nights. For contractors who work behind schedule, EVN/EVNNPT and the project management boards request contractors to add more capable subcontractors to speed up progress.

For contractors who are overloaded and behind schedule, the investor also asked to add more capable subcontractors to speed up the production and supply of columns. For imported steel column packages, contractors worked with manufacturing partners to increase production and speed up production and delivery of products before May 30, 2024.

The investors set the target to finish putting up all the columns on June 15, complete the installation of insulation, accessories, and wire pulling on June 20, and perform testing, acceptance, and energisation from June 20-30.

EVNNPT accelerates 500kV transmission line from Quang Trach to Pho Noi

To ensure the progress of the 500kV circuit 3 Quang Trach - Pho Noi line project to be completed in June 2024, EVNNPT mobilised 800 skilled human resources from power transmission companies across the country to participate in construction.

These engineers and skilled workers are mobilised from Power Transmission Company No.4, Power Transmission Company No.3, Power Transmission Company No.2 and Power Transmission Company No.1.

Nguyen Ba Dung, deputy director of Quang Ngai Power Transmission under Power Transmission Company No.2, said, “Immediately after the request of EVNNPT, the National Power Transmission Company No.2 took about 120 engineers and skilled workers to establish five construction teams to erect poles and pull ropes to support construction contractors.”

Huynh Quang Thinh, head of Technical Department at Power Transmission Company No.3, said, “For each position assigned to erect a pole, in favourable weather conditions, we will carry out construction within 15 to 20 days to complete a column position with a column erection volume of over 100 tonnes. Each engineer and worker determined to complete the column erection will work synchronously with other units.”

500kV transmission line project from Quang Trach to Pho Noi

Investor: National Power Transmission Corporation (under EVN)

Total investment: about VND22 trillion ($916.6 million)

Scale: 2 circuits of 500kV transmission line, about 519km long. Starting point is 500kV Quang Trach switchyard (Quang Binh), ending point is 500kV Pho Noi substation (Hung Yen).

Engineering consultant: Power Engineering Consulting JSC 1, 2, 4 and Institute of Energy

Project Management Board for Northern Power Projects on behalf of EVNNPT manages two sections: Nam Dinh I Thermal Power Plant – Thanh Hoa and Nam Dinh I Thermal Power Plant - Pho Noi.

Project Management Board for Central Power Projects on behalf of EVNNPT manages two sections: Quang Trach – Quynh Luu and Quynh Luu - Thanh Hoa

EVNNPT in solid position after 15 years EVNNPT in solid position after 15 years

National Power Transmission Company (EVNNPT) has made significant achievements and contributed greatly to ensuring national energy security in the 15 years since its establishment.

EVNNPT accelerates construction of Nho Quan-Phu Ly-Thuong Tin transmission line EVNNPT accelerates construction of Nho Quan-Phu Ly-Thuong Tin transmission line

National Power Transmission Corporation (EVNNPT) is expediting the construction of the 500/220kV Nho Quan-Phu Ly-Thuong Tin transmission line.

EVNNPT to loan $675 million for Quang Trach-Pho Noi 500kV line EVNNPT to loan $675 million for Quang Trach-Pho Noi 500kV line

National Power Transmission Corporation will mobilise loans worth $675 million for part of the construction of the Quang Trach-Pho Noi 500kV transmission line project.

EVN and EVNNPT to upgrade power transmission lines in Thai Binh EVN and EVNNPT to upgrade power transmission lines in Thai Binh

Vietnam Electricity (EVN) will co-operate with National Power Transmission Corporation (EVNNPT) and Thai Binh People’s Committee to resolve the issues relating to the power transmission lines in the northern province.

EVNNPT prepares plans to implement 500kV projects EVNNPT prepares plans to implement 500kV projects

The approval of the 500kV line for the Nam Dinh I-Thanh Hoa thermal power plant will help accelerate the construction of Circuit 3's Quang Trach-Pho Noi 500kV line project.

By Hoang Nam

What the stars mean:

★ Poor ★ ★ Promising ★★★ Good ★★★★ Very good ★★★★★ Exceptional