| 1,500 MW LNG power plant project in Thanh Hoa required to be revived. Photo: chinhphu.vn |
At a meeting on October 21, Deputy Prime Minister Pham Gia Tuc asked that Thanh Hoa People's Committee, along with relevant ministries and Cong Thanh Thermal Power Plant JSC, the project’s investor, work together to issue plans to continue construction.
At the meeting, leaders of Thanh Hoa People's Committee stated that the locality had worked with the investors many times; however, the project still had several issues that needed review and completion regarding investment procedures, conditions, and implementation plans.
“Resolving the obstacles requires a thorough review of the entire previous investment process and the conversion from coal-to LNG-fired power. Relevant agencies need to clearly identify the remaining issues, the responsibilities of each stakeholder, and feasible solutions,” DPM Tuc said.
“Regarding relevant infrastructure, the province and the investor need to agree on a suitable plan that harmonises the interests of all parties. In particular, the parties should prioritise utilising existing facilities in the area according to the plan. The investor is responsible for completing the procedures and demonstrating its financial capacity and project implementation plan. The implementation process must have specific milestones, clearly defining the responsibilities and commitments of each stakeholder," he said.
The Cong Thanh thermal power project broke ground in 2011 with a coal-fired capacity of 600 MW and an initial investment of approximately $1.2 billion. According to the original plan, its two turbines were scheduled to go into operation in 2014.
After nearly 11 years of delays due to difficulties in arranging capital, in July 2022, the province proposed switching to using LNG, increasing the capacity to 1,500 MW. This plan was updated in the adjusted Power Development Plan VIII in April 2025. This project is included in the list of national important projects, key projects in the energy sector, and was expected to be operational in 2031-2035.
In August 2025, Cong Thanh Thermal Power JSC and a consortium of South Korea’s Doosan Enerbility and Vietnam’s Power Engineering Consulting JSC 2 signed a principle agreement on the implementation of the project. However, the construction has yet to continue.
Cong Thanh's plant is one of 18 long-delayed LNG-fuel projects in Vietnam. Of the 18 LNG power plant projects under monitoring with a total capacity of over 20,000 MW, 16 projects have completed the investor selection process, while the remaining two projects, namely Nghi Son LNG and Long Son LNG, still have not selected investors.
In May, Nghi Son Economic Zone Management Authority had to cancel the bidding to select the investors for the Nghi Son LNG-fired thermal power project for the third time, as zero dossiers were submitted.
Of the 16 projects that already have investors, only two have actually commenced construction, while 14 are still in the process of finalising investment preparations.
| Land clearance contract for new thermal power plant to be signed Nghe An People's Committee require the consortium of investors in the Quynh Lap LNG thermal power plant to sign the land clearance contract with the local authorities before September 25. |
| JBIC considers new financing options for Vietnam’s energy projects Vietnam’s substantial capital requirements for achieving high economic growth are driving efforts to diversify domestic and international funding channels. The Japan Bank for International Cooperation has expressed its readiness to support Vietnam in energy and infrastructure projects, as well as efforts to raise capital in international markets. |
| LNG power plant projects risk falling behind schedule Of the 18 liquefied natural gas (LNG) power plant projects with a total capacity of over 20,000 MW, only two have commenced construction, and only the Hiep Phuoc LNG project is assessed as likely to be on schedule. |
| Long-delayed LNG power projects may be replaced in revised PDP VIII The Ministry of Industry and Trade is consulting ministries and localities for the adjustment of Power Development Plan VIII - Phase 1. One of the contents is the proposal to replace coal-fired or gas-fired power plants with LNG power projects in the north. |
| Vung Ang LNG Terminal looks for candidates for $1 billion EPC contract Vietnam Gas Corporation is seeking a contractor to provide the engineering, procurement, and construction package for the Vung Ang LNG Terminal project. |
| Petronas, Petrovietnam to expand energy cooperation Malaysia’s national oil and gas company Petronas will continue working with Petrovietnam on oil and gas exploration and production, LNG supply and renewable energy development in the coming years. |
What the stars mean:
★ Poor ★ ★ Promising ★★★ Good ★★★★ Very good ★★★★★ Exceptional