PM calls for completion of 500kV Circuit-3 transmission line by National Day

July 23, 2024 | 10:28
(0) user say
Prime Minister Pham Minh Chinh has called for the completion of the 500kV Circuit-3 transmission line on the occasion of the 79th anniversary of August Revolution and National Day (September 2).
PM calls for completion of 500kV Circuit-3 transmission line by National Day
PM calls for completion of 500kV Circuit-3 transmission line by National Day

Hanoi – Prime Minister Pham Minh Chinh has called for the completion of the 500kV Circuit-3 transmission line by the 79th anniversary of August Revolution and National Day (September 2).

The 519km transmission line, stretching from Pho Noi in the northern province of Hung Yen to Quang Trach in the central province of Quang Binh, traverses nine provinces and has a cost of around 22 trillion VND (916 million USD).

Its construction began in January 2024 to meet growing demand for power in peak times. Compensation and site clearance have already been completed, paving the way for swift progress.

Chairing a meeting with ministries, agencies and localities on July 22, the fourth of its kind in the past sixth months, PM Chinh said the project holds significance to socio-economic development, national defence-security and social welfare of localities it serves.

He urged ministries, agencies, localities and units to redouble their efforts, strengthen unity, boost determination and effectiveness to complete the project with the highest sense of responsibility.

Specific tasks were also assigned to the Ministry of Industry and Trade, the Vietnam Electricity (EVN), the National Power Transmission Corporation (EVNNPT), and others to ensure that all aspects of the project are carried out smoothly and on time.

EVNNPT prepares plans to implement 500kV projects EVNNPT prepares plans to implement 500kV projects

The approval of the 500kV line for the Nam Dinh I-Thanh Hoa thermal power plant will help accelerate the construction of Circuit 3's Quang Trach-Pho Noi 500kV line project.

EVNNPT accelerates 500kV transmission line from Quang Trach to Pho Noi EVNNPT accelerates 500kV transmission line from Quang Trach to Pho Noi

EVNNPT has mobilised more than 800 engineers and skilled workers to participate in erecting poles and pulling wires for the 500kV transmission line circuit 3 from Quang Trach to Pho Noi project to ensure the key national project is on time.

500kV transmission line switched on between Nam Dinh I TPP and Thanh Hoa 500kV transmission line switched on between Nam Dinh I TPP and Thanh Hoa

A 500kV circuit-3 transmission line officially went live on the Nam Dinh I TPP - Thanh Hoa section on June 30.

By VNA

What the stars mean:

★ Poor ★ ★ Promising ★★★ Good ★★★★ Very good ★★★★★ Exceptional