Shake-up for solar power investment

February 27, 2021 | 14:00
(0) user say
The Electricity and Renewable Energy Authority of Vietnam has submitted a report that requests approval of the prime minister’s draft decision on selection of investors for grid-connected solar power projects in Vietnam. Baker McKenzie’s managing partner Frederick Burke and special counsel Nguyen Thanh Hai outline the main changes and proposed regulations for investors.
1532 p8 shake up for solar power investment
Baker McKenzie’s managing partner Frederick Burke and special counsel Nguyen Thanh Hai

The contents of the decision circulated on January 21 is in draft form, while final contents are subject to further reviews by the Ministry of Industry and Trade (MoIT), and consultations with other relevant ministries before the prime minister’s final signature.

This draft decision would apply the selection mechanism on a long-term basis. Bidding rounds will be conducted based on a so-called Renewable Energy Development Plan formulated by the MoIT for each 5-year period. A more specific plan will be circulated on a biannual basis.

The main investor selection mechanism is a so-called “competitive selection of investors based on project location”, which means that: (i) project location will be chosen/determined by the governmental authorities; and (ii) investors must submit bids to compete for securing the project development right at that pre-selected project location.

Under this draft decision, the bidding mechanism would be conducted at the local level by provincial-level people’s committees, rather than by the MoIT at nationwide level.

As regards power sale/purchase price, the current draft provides that the ceiling price will be subject to a specific pricing framework, which will be prepared and issued by the MoIT on a biannual basis.

In addition, the draft decision proposes detailed regulations on eligibility requirements for investors participating in this mechanism, bidding procedures and requirements for selected investors. Notably, it also makes a reference to a model power purchase agreement (PPA) template, but as the full text of such template has yet to be completed, it remains uncertain as to whether there would be any or significant improvements to the risk allocation and bankability of this proposed template for new renewable energy projects under this reverse auction mechanism.

1532 p8 shake up for solar power investment
The prime minister’s draft decision includes a bidding mechanism conducted at the local level rather than by the MoIT at nationwide level, Photo: shutterstock

Recommended considerations

There are specific intentions under this draft which relate to overall legal mechanisms and for renewable projects in Vietnam, such as upcoming regulations related to the solar auction/competitive bidding programme; necessary legal considerations for existing and newly proposed solar farms to best prepare for participation in competitive selection mechanisms; specific selection procedures as proposed under the draft decision; and specific opportunities and challenges, as well as legal and practical solutions for development and investment in greenfield solar power projects in Vietnam.

The investor selection mechanism proposed under this decision applies to all solar power projects directly connected to the national power grid. Under the draft, a solar power project may be approved for development through either competitive selection of investors based on the project’s location, or investor approval.

Most parts provide guidelines for the former method. On the other hand, no specific guidance on the latter method was provided, but as a general rule of law, the method must be subject to the new Law on Investment as well as the investor appointment mechanism under the current bidding regulations.

It is also worth noting that all of these will be subject to more guidelines specific to the solar and renewable energy sector to be provided in the final draft.

Eligibility requirements

The draft decision does not impose any restriction on participation by foreign investors. However, participating investors must be independent from each other. This requirement may limit the number of proposed projects and chance of success in the bids of certain investors.

For example, an investor must not be named in technical proposals for two or more proposed projects whether as an independent investor or as a consortium of multiple investors; and an investor must not own more than 20 per cent capital of another investor participating in the bids.

In addition, the participating investors must submit, together with the bid proposals, certain documents demonstrating their experience and financial capability, such as financial statements in the last two years and evidence of the capability to mobilise investment capital (both equity financing and debt financing).

Power sale tariff

For selected projects, the electricity tariff is set at the rate proposed by the winning investors in the bidding process. Among the investors that have met all eligibility and technical requirements, as a general rule, the investors proposing the lowest power tariff will be selected to sign a PPA with Electricity of Vietnam (EVN).

The applicable tariff will apply for 20 years from commercial operation date (COD) of the project and will be subject to the USD-VND exchange rate fluctuation based on the central exchange rate announced by the State Bank of Vietnam on the invoicing date.

To ensure the feasibility and enforcement of the proposed tariffs, the draft decision requires that the electricity tariff formulated by participating investors must take into account, among other things, project development costs determined in compliance with the construction law and solar power regulations; and grid connection costs.

For selected projects, if the project fails to reach COD as proposed during the bids, under the draft, the electricity tariff under the project PPA will be reduced by a cumulative portion of 4 per cent after each 90-day period of delay/falling behind the originally proposed schedule.

Selection procedures

The draft decision sets out the following key procedures:

- The MoIT prepares/adopts the 5-year renewable energy plan based on (among other things) the power development master plan and the status of the local power grids. This plan specifies a total capacity for each type of renewable energy source for a 5-year period; and a list of transmission lines and substations (with voltages from 220kV) coming into operation during the 5-year period.

- In each 2-year period, based on the 5-year renewable energy plan, the MoIT prepares/adopts a 2-year periodical solar development plan, which specifies the total solar power capacity to be developed in each province/city; and a list of 110kV/220 kV/550 kV transmission lines and substations that are capable of absorbing power generated from renewable energy projects.

- On a biannual basis, provincial people’s committees (PPCs) prepare solar investor selection plans under their local management for the province based on (and no later than six months from issuance of) the MoIT’s 2-year periodical solar development plan. This selection plan must specify the project locations that will be opened to bidding.

- PPCs submit the draft solar investor selection plan to the MoIT and EVN for their appraisal/comments, prior to PPC adoption and publication of their selection plan.

- Participating investors submit proposals to relevant PPCs, with a separate technical proposal and a separate commercial/electricity tariff proposal.

- PPCs evaluate the submitted proposals, select projects, and sign PPAs for selected projects/winning investors.

There are other notable requirements for investors. The draft decision requires a bid guarantee of 0.5 per cent, the total investment capital of the participating project. Forms of bid guarantees to be submitted, as well as conditions for returning bid guarantees have yet to be specified at this stage under the draft.

For selected projects, it also requires investors to sign a “project development commitment letter” based on the contents of the bid proposals. Investors must also deposit an investment project implementing security in the bank accounts of the local authority or other forms in accordance with the new Law on Investment.