$2.35 billion Quang Tri thermal power project terminated

$2.35 billion Quang Tri thermal power project terminated

EGAT has officially announced the termination of the Quang Tri thermal power project after construction was delayed for over a decade.
EGATi has yet to get Thai government approval for Quang Tri 1 thermal power plant

EGATi has yet to get Thai government approval for Quang Tri 1 thermal power plant

The Thai government has yet to license EGATi, the investor of Quang Tri 1 thermal power plant, to invest overseas, making construction plans uncertain.
Construction of Quang Tri 1 thermal power plant deemed unfeasible

Construction of Quang Tri 1 thermal power plant deemed unfeasible

Despite the investor's commitment to start the construction of the Quang Tri 1 thermal power plant in September, to date, the site remains vacant.